Schedule for VMS and Gantry Installation works |
|
|
January 2004 Date: 2nd January 2004 (Friday)
No. Of Days
|
Location
|
Time
|
Nature of Work
|
Road Closure
|
2
|
Jalan Ampang
|
10.00am - 11.00am
|
Installation Of VMS Board And Gantry
|
1 lane closure
|
11.00am - 1.00pm |
Date: 3rd January
2004 (Saturday)
No. Of Days
|
Location
|
Time
|
Nature of Work
|
Road Closure
|
2
|
Jalan Ampang
|
10.00pm - 11.00am
|
Traffic management set-up for road shoulder
foundation work |
1 lane closure
|
11.00pm - 4.00pm |
Piling work for road shoulder foundation |
10.00pm - 11.00pm |
Traffic management setup for road-median foundation work (if
necessary) |
11.00pm - 4.00am |
Piling work for road shoulder foundation (if necessary) |
Date: 4th January
2004 (Sunday)
No. Of Days
|
Location
|
Time
|
Nature of Work
|
Road Closure
|
2
|
Jalan Ampang
|
10.00am - 11.00am
|
Traffic management set-up for road shoulder
foundation work
|
1 lane closure
|
11.00am - 4.00pm
|
Excavation and formwork
|
10.00pm - 11.00pm
|
Traffic management setup for road-median
foundation work
|
11.00pm - 4.00am
|
Concrete pouring for road shoulder foundation
work
|
Date: 5th January
2004 (Monday)
No. Of Days
|
Location
|
Time
|
Nature of Work
|
Road Closure
|
2
|
Jalan Ampang
|
10.00am - 11.00am
|
Traffic management set-up for road shoulder
foundation work
|
1 lane closure
|
11.00am - 4.00pm
|
Remove formwork & backfill for V56 road-shoulder
foundation
|
Date: 6th January
2004 (Tuesday)
No. Of Days
|
Location
|
Time
|
Nature of Work
|
Road Closure
|
2
|
Jalan Kinabalu / Jalan Kuching
|
10.00pm - 11.00pm
|
Traffic management set-up for VMS and Gantry
Installation work
|
1 lane closure
|
11.00pm - 11.30pm
|
Downloading Gantry structure, installing
VMS board and
frame onto structure
|
11.30pm - 12.00am
|
Installation of Gantry Horizontal Structure
|
12.00am - 1.30am
|
Mobilization to V125 site
|
Date: 7th January
2004 (Wednesday)
No. Of Days
|
Location
|
Time
|
Nature of Work
|
Road Closure
|
2
|
Jalan Ampang
|
10.00am - 11.00am
|
Traffic management set-up for road shoulder
foundation work
|
1 lane closure
|
11.00am - 4.00pm
|
Excavation and formwork
|
10.00pm - 11.00pm
|
Traffic management setup for road-median
foundation work
|
11.00pm - 4.00am
|
Concrete pouring for road shoulder foundation
work
|
Date: 8th January
200 (Thursday)
No. Of Days
|
Location
|
Time
|
Nature of Work
|
Road Closure
|
6
|
Jalan Ampang
|
10.00am - 11.00am
|
Traffic management set-up for road median
foundation work
|
1 lane closure
|
11.00pm - 4.00pm |
Remove formwork & backfill for V56 road-shoulder
foundation |