Schedule for VMS and Gantry Installation works |
|
|
December 2003
Date: 11th
December 2003 (Thursday)
No. Of Days
|
Location
|
Time
|
Nature of Work
|
Road Closure
|
6
|
Lebuhraya Mahameru (Towards Jalan Tun Razak)
|
10.00am - 04.00pm
|
Foundation Work
|
1 lane closure
|
Date: 11th
December 2003 (Thursday)
No. Of Days
|
Location
|
Time
|
Nature of Work
|
Road Closure
|
6
|
Jalan Ampang (Toward MRR 2)
|
10.00am - 04.00pm
|
Piling & Foundation Work
|
1 lane closure
|
Date: 12th
December 2003 (Friday)
No. Of Days
|
Location
|
Time
|
Nature of Work
|
Road Closure
|
6
|
Jalan Ampang (Toward MRR 2)
|
10.00am - 04.00pm
|
Piling & Foundation Work
|
1 lane closure
|
Date: 13th
December 2003 (Saturday)
No. Of Days
|
Location
|
Time
|
Nature of Work
|
Road Closure
|
6
|
Jalan Ampang (Toward Jln Tun Razak)
|
10.00am - 04.00pm
|
Piling & Foundation Work
|
1 lane closure
|
Date: 14th
December 2003 (Sunday)
No. Of Days
|
Location
|
Time
|
Nature of Work
|
Road Closure
|
6
|
Jalan Ampang (Toward MRR 2)
|
10.00am - 04.00pm
|
Piling & Foundation Work
|
1 lane closure
|
Date: 14th
December 2003 (Sunday)
No. Of Days
|
Location
|
Time
|
Nature of Work
|
Road Closure
|
6
|
Lebuhraya Mahameru (Towards Jalan Tun Razak)
|
10.00am - 04.00pm
|
Foundation Work
|
1 lane closure
|
Date: 15th
December 2003 (Monday)
No. Of Days
|
Location
|
Time
|
Nature of Work
|
Road Closure
|
6
|
Jalan Ampang (Toward Jln Sultan Ismail)
|
10.00am - 04.00pm
|
Piling & Foundation Work
|
1 lane closure
|
Date: 29th
December 2003 (Monday)
No. Of Days
|
Location
|
Time
|
Nature of Work
|
Road Closure
|
6
|
Jalan Ampang
|
10.00pm - 11.00am
|
Traffic management set-up for road shoulder
foundation work
|
1 lane closure
|
11.00pm - 1.00pm |
Excavation and formwork for road shoulder foundation (toward
KL city) |
1.00pm - 2.00pm |
Traffic management setup for road-median foundation
work |
3.00pm - 4.00pm |
Concrete pouring for V12/V13's foundation |